「Cat Global」のベントナイト猫砂の製造工程 ― 工場見学

目次

A walkthrough of every step that turns raw sodium bentonite into a bag of Cat Global bentonite cat litter — from raw-material intake through dust extraction, fragrance loading, OEM customisation, and final QC.

Need the spec floor first? See the ナトリウムベントナイト 仕様書. For the buyer’s perspective, see the bulk B2B buying guide.

「Cat Global」のベントナイト猫砂の製造工程 ― 工場見学

1. The Aisha-Pet factory — production base


Cat Global bentonite cat litter is produced at アイシャ・ペット — the in-house factory of PY-PET(普源大連ペット製品有限公司) in Dalian, China. Aisha-Pet sits on an 18,000 m² integrated facility in the Dalian Economic & Technological Development Zone, operates 12 production lines, and runs at 6,000 tons / month total capacity across all substrates. The bentonite line occupies 4 of the 12 lines.

The factory is the same legal entity as the Cat Global brand owner — PY-PET is the company, アイシャ・ペット is its factory name, キャットグローバル is its customer-facing brand. One company, one factory, one quality system.

2. The bentonite production line — 7 stages


2.1 Stage 1 — Raw-material intake and screening

Sodium bentonite arrives at Aisha-Pet in 1 MT bulk bags or 25 kg sacks, sourced from Wyoming-grade sodium-bentonite mines. Each shipment is sampled and tested on arrival for:

  • 腫脹指数 — must be ≥ 12× dry volume (rejection band: < 10×)
  • 水分 — must be ≤ 12% on arrival (rejection band: > 15%)
  • Heavy metals — SGS-tested against the Cat Global spec (Pb ≤ 5 mg/kg, As ≤ 2 mg/kg, Cd ≤ 1 mg/kg)
  • Visual inspection — no off-color clay, no contamination

Approved raw material moves to the climate-controlled silo (≤ 25°C, ≤ 70% RH). Rejected batches are returned to the supplier with the test report.

2.2 Stage 2 — Crushing and granulation

The raw bentonite is fed into a jaw crusher (for the initial size reduction) followed by a roll crusher (for the target granule shape). The crushed bentonite is screened into the three standard shapes — round (1.6–2.5 mm), ball (2.0–3.0 mm), crushed (1.5–4.0 mm). Custom shapes for OEM programs are run on the same line with a swapped screen pack.

Granule size distribution is checked in-process every 30 minutes via laser-diffraction particle sizer. Out-of-spec material is recycled back into the crusher feed.

2.3 Stage 3 — Dust extraction (the critical step)

This is the step that turns value-tier bentonite (2–3% dust) into premium low-dust bentonite (≤ 0.5% dust). The crushed bentonite passes through a multi-stage cyclone dust-extractor — air is drawn through the granule stream and the < 75 μm dust fraction is separated and collected for off-spec use (industrial absorbents, etc.).

Cat Global’s dust-extraction system targets ≤ 0.5% residual dust on the final product. After the cyclone, the granule stream passes through a vibrating-deck fines separator for a final pass. In-line laser particulate counter measures the dust fraction every 15 minutes.

2.4 Stage 4 — Fragrance loading

For scented SKUs, fragrance oil is sprayed onto the bentonite granules in a rotating mixer. Fragrance load is tuneable between 0.05% and 0.40% depending on SKU. The 8 stock fragrances (Unscented / Apple / Lemon / Lavender / Rose / Green Tea / Coffee / Baby Powder) are pre-mixed in 200 L drums; the spray rate is calibrated per SKU.

Custom fragrance profiles (ocean breeze, white musk, jasmine, mango) are available for OEM programs above 5 MT per SKU. Fragrance load is verified every batch via gas chromatography on the in-house QC lab.

2.5 Stage 5 — Packaging

The finished bentonite is packed via automated weigh-fill-seal lines into the configured pack size:

  • 5 kg pack — PE inner bag + Kraft paper outer, 4 bags per master carton
  • 10 kg pack — PE inner bag + Kraft paper outer, 2 bags per master carton
  • 20 kg pack — PE inner bag + woven PP outer, single-bag (no master carton)
  • 5 L / 10 L / 25 L pack — PE inner bag + printed woven outer (or printed PE for shelf)
  • Custom OEM pack — printed PE / Kraft / woven to buyer spec

Pack-weight tolerance: ± 1% (Cat Global QC spec). Seal-integrity check on every bag via pressure-decay test. Master cartons are labelled with SKU code, batch number, production date, and expiry date.

2.6 Stage 6 — Palletisation (optional)

For shelf-ready delivery or container-optimised shipping, finished cartons can be palletised on fumigated ISPM-15 wooden pallets (1.0 × 1.2 m standard) with shrink-wrap. A standard pallet holds 800 – 1,200 kg of finished bentonite depending on pack size.

Palletised containers load approximately 5% more efficiently than loose cartons because of the better cube utilisation.

2.7 Stage 7 — Container loading, documentation, and dispatch

The finished pallets or loose cartons are loaded into 20FT or 40HQ containers. Loading is done under cover to prevent rain ingress. On the day of FOB Dalian, the buyer receives:

  • Loading photo (with timestamp + container number)
  • Container number
  • COA (Certificate of Analysis — per batch)
  • SGS test report (third-party)
  • MSDS(製品安全データシート)
  • COO (Certificate of Origin — for tariff preference)
  • Health Certificate (issued by CIQ)
  • Fumigation Certificate (when palletised)
  • Commercial Invoice + Packing List
  • Regional add-ons: ANVISA / MERCOSUR / GSO / GCC / FDA Philippines as required

3. In-process QC checkpoints


ステージ QC check 周波数 Method
Raw intake Swelling index, moisture, heavy metals Every shipment In-house + SGS
Post-crush Granule size distribution Every 30 min Laser diffraction
Post-dust-extraction 粉塵含有量 Every 15 min Laser particulate counter + 200-mesh sieve
Post-fragrance-load Fragrance load % Every batch Gas chromatography
Post-pack Pack weight + seal integrity Every bag Weigh-scale + pressure-decay test
Final batch Clumping strength, deodorisation, dust, heavy metals Every batch SGS third-party

Every batch retains a 1 kg reference sample for 12 months post-shipment. If the buyer reports a quality issue, the reference sample can be re-tested to confirm whether the issue was batch-specific or post-shipment contamination.

4. OEM customisation workflow


For OEM buyers (private-label programs, shelf-ready packs, custom fragrance profiles), the production line accepts the following customisation parameters:

Customisation 最小注文数量(MOQ) Lead time impact
Custom artwork on outer pack 1 × 20フィート + 5 – 8 days (printing plate changeover)
Custom fragrance profile 5 MT per SKU + 10 – 14 days (fragrance sourcing + GC calibration)
Custom granule shape 5 MT per SKU + 7 – 10 days (screen-pack tooling)
Custom fragrance load % 1 × 20フィート + 2 – 3 days (spray calibration)
Custom pack size (non-standard) 1 × 20フィート + 7 – 14 days (bag-production tooling)
Custom master carton design 1 × 20フィート + 5 – 8 days (carton tooling)

For OEM customisation beyond the stock specifications, Cat Global’s design team handles layout, translation and back-panel compliance 無料 for OEM programs above 1 × 20FT.

5. The 5-step OEM process (buyer side)


For the buyer’s perspective, the OEM process is the same 5 steps used by Cat Global’s existing partners:

  1. Submit your brief — target market, shelf price tier, granule shape, fragrance profile, fragrance load, pack format, destination-market documentation. (Day 0–2)
  2. Sample + formula lock — 5–10 kg free sample, freight collect. Iterate on clumping, fragrance throw, dust level, granule feel. Lock in writing. (Day 3–14)
  3. Artwork + packaging design — send your your artwork or use our free in-house design service. 3D mock-up + printed-on-bag proof + translated back-panel compliant with destination market (ANVISA, GSO, MERCOSUR, GCC). (Day 10–18)
  4. Production + third-party QC — production on a dedicated line, in-process QC at every stage. SGS dust + heavy-metal + swelling-index testing on the final batch before shipping. (Day 18–32)
  5. Ship + documentation — loading photo + container number + full document set (COA, MSDS, COO, SGS report, Commercial Invoice, Packing List) sent on the day of FOB Dalian. CIF / DDP quoted per destination lane. (Day 32+ · ≤ 20 days after deposit)

End-to-end OEM program duration: 32–40 days total. Standard SKU lead time: ≤ 20 days after deposit.

6. What a factory tour looks like


B2B buyers are welcome to visit the Aisha-Pet factory for an in-person tour. The standard tour takes 3–4 hours and covers:

  • Raw-material warehouse (sodium bentonite silos + sample library)
  • Production line walkthrough (crusher → dust extractor → fragrance loader → pack line)
  • In-house QC lab (laser particle sizer, gas chromatograph, 200-mesh sieve station)
  • Finished-goods warehouse (climate-controlled, batch-tracked)
  • Loading dock (container-loading observation, optional)
  • Export documentation review (COA / SGS / COO samples from recent shipments)

Tours are scheduled with 2 weeks’ notice. Buyers are paired with their dedicated account manager for the visit. Send your preferred dates via the お問い合わせフォーム and we’ll book the visit.

7. Capacity and scaling


Aisha-Pet operates 4 dedicated bentonite production lines, with total bentonite capacity of approximately 1,800 – 2,200 MT / month (vs the 6,000 T/month factory total across all substrates). Peak season (October – February for the Middle East and South America buying cycles) runs at ~ 90% utilisation; off-peak runs at ~ 60%. This headroom means new-buyer 20FT pilots can typically be scheduled within 14 days of deposit.

この記事を共有する

LinkedIn
フェイスブック
ツイッター
レッドディット
ピンタレスト

その他の投稿

24時間以内のお見積もりをご依頼ください →

25年の実績を持つメーカーから猫用トイレ砂を仕入れる準備はできていますか?

今すぐお問い合わせください。24時間以内にお客様に合わせたお見積もりをご提示し、2日以内に無料サンプルをお届けします。30日以内にプライベートブランド事業を開始できます。.

お問い合わせc